Monday, January 2, 2017

Kitchen Construction, Part 6 - Fabulous Flooring

Before
Our kitchen had terrible tile floors. It was a crappy design with a super glossy finish that showed every speck of dirt. It had to go.
I started the demolition with my trusty hammer, but it was slow going.

I quickly switched to a "landscape bar" and things went much faster.

You can see I took precautions to contain the debris and protect the fridge.

After some extensive cleanup, we had a beautiful concrete floor, which we lived with for quite some time.

After filling the trash can with as much weight as was advisable, we had a nice pile leftover for subsequent weeks

The tile and thinset came up surprisingly cleanly, but there were some rough patches that I marked as I found them and eventually ground down with my oscillating tool.

Whoever installed the tile put a thin row of tile on the toe kick under the counters. I ripped that off, along with a thin sheet of plywood underneath.

I then primed the toe kick, which was a ton of fun.

Once we finally got around to laying the tile, we did a fairly intense dry-run to make sure we got the layout right.

This is what our living room looked like when we were doing the tile. We actually got used to having the fridge there and would walk into the living room to get ice even after everything was back in place.

Laying the tile proved to be more difficult and time consuming than expected, but we did our best.

We worked late into the night, until everyone was exhausted. I have to give a huge THANK YOU to my buddy Tai, who helped a ton, and also lent us the tile saw.

Eventually, we laid the last tile.

And the floor was done.

After a little cleanup it looked pretty good. All the tiles aren't quite as even as we would like, but it's good enough.

Unfortunately, we weren't careful enough about cleaning out between the tiles where thinset came up. That would have created a problem for the grout, so I got to go along every crack and grind it out. I used the oscillating tool with the diamond blade for the first pass, then held the blade in my hand and smoothed everything out on the second pass.

Once that was done, it was time for grout. Applying the grout was very satisfying. Sponging off the excess--not so much.

After the grout dried we applied a sealer, which finished off the tile work, but not the flooring project.

There was still a lot of trim to be installed. I started with some quarter round under the cabinets to cover the 1/8 inch gap we intentionally left all the way around.

There were also unsightly gaps between the tile and laminate, which I filled with real wood T molding.

I got to make some nice custom cuts to pieces that go above the T molding.

The last step I performed was adding a bead of clear silicone between the T molding and the tile.

This isn't the best photo of the finished product, but you get the idea.
After
If you thought that was the end of the story, you are sorely mistaken, because we also replaced the entryway tile at the same time, which was a lovely shade of green.

I smashed it out just like the kitchen, but it didn't come up as cleanly. It took a lot of extra work to get it all smoothed out.

One of the pieces of tile shrapnel actually cut my leg. It bled a lot more than expected.

We laid the actual tile the same day we did the kitchen. It was really late when we finished the kitchen, and we were so relieved, until we remembered we still had to do the entryway. But we finished it and it looked pretty good.

I put down the same T molding as in the kitchen, along with some quarter round along the wall and under the door.

For the trim under the door, I had to remove 5mm of material to clear the door. That was a fun cut on the table saw.

In the end it came out beautifully. 
After

1 comment:

  1. Looks really good! Great use of the oscillating tool to clean between the tiles, big time saver.

    ReplyDelete